The Light Rail Manila Corporation (LRMC) welcomed the new year with a notable achievement, as it recently celebrated the completion of the first phase of the LRT-1 Cavite Extension viaduct.
The project started in September 2019, when LRMC and Bouygues Travaux Publics started civil works by installing pi-girders at the Parañaque City start point. The pi-girders covered the entire stretch of Dr. A. Santos Station until Redemptorist Station in Parañaque.
With the viaduct now complete, LRMC remains focused on electromechanical works, specifically laying the railway and installing the electrical systems. The new stations will also reportedly begin construction.
Phase 1 of the LRT-1 Cavite Extension project includes five stations: Dr. A Santos, Ninoy Aquino, Asiaworld, MIA, and Redemptorist. The total completion rate stood at 67.5% as of December 2021.
Upon completion, the project will benefit residents South of Manila, including Parañaque, Las Piñas, Cavite, and nearby cities and provinces. Some stations will also connect to public transport terminals for better integration and convenience. According to LRMC, it aims to complete the project by late 2024 or early 2025.
For now, we'll have to celebrate each small victory on the way to a fully functional LRT-1 Cavite Extension. The project is a few years away from usability, but it will help countless commuters get in and around Metro Manila in due time.
"LRMC is glad to welcome 2022 with this LRT-1 Cavite Extension accomplishment. I am proud of the commitment and sacrifice of all our teams, who displayed resilience amidst unsettling conditions and the determination to deliver with excellence. With the support from our various partners in the public and private sectors, this project was able to achieve significant progress despite the limitations of the pandemic. Through our work in upgrading and extending the LRT-1 system, we hope to make a difference and improve the lives of future generations." - Juan F. Alfonso, President, and CEO, LRMC
LRMC is glad to welcome 2022 with this LRT-1 Cavite Extension accomplishment. I am proud of the commitment and sacrifice of all our teams, who displayed resilience amidst unsettling conditions and the determination to deliver with excellence. With the support from our various partners in the public and private sectors, this project was able to achieve significant progress despite the limitations of the pandemic. Through our work in upgrading and extending the LRT-1 system, we hope to make a difference and improve the lives of future generations.
Latest News
-
Isuzu D-MAX, mu-X post standout performance in 2025 DOE Fuel Eco-Run / News
Isuzu proves its fuel-sipping diesel edge as the D-MAX and mu-X post impressive results in the 2025 DOE Fuel Eco-Run.
-
Kia’s keeping the manual and wagons alive with the K4 Sportswagon / News
Kia reveals the K4 Sportswagon, a stylish estate offering turbo engines, modern tech, and of course, a large cargo bay.
-
Leaked images of the next-gen Nissan Versa might be a glimpse into the new Almera / News
Leaked images of what might be the next-gen Versa have surfaced online. Could this also be the next Almera?
Popular Articles
-
Electric Vehicles in the Philippines for under P1 million
Jerome Tresvalles · Aug 19, 2025
-
Top 3 Cars For Every Lifestyle—What Cars Are Right For You? | Behind a Desk
Caco Tirona · Apr 24, 2024
-
5 Tips to Maximize Fuel Efficiency
Jerome Tresvalles · Sep 09, 2024
-
Five driving habits that are draining your fuel tank
Jerome Tresvalles · Jun 24, 2025
-
Can engine braking harm your engine?
Jerome Tresvalles · Sep 11, 2025
-
Do electric cars even need maintenance?
Jerome Tresvalles · Oct 23, 2024
-
Best vehicles for an active outdoor lifestyle
Shaynah Miranda · Jul 25, 2024
-
How to drive different types of vehicle transmissions
May 23, 2024
-
5 easy ways to keep your car interior clean
Allysa Mae Zulueta · Nov 15, 2021
-
How to survive Metro Manila traffic
Earl Lee · Aug 16, 2022